Direct answer: a serious turnkey construction contract protects the client across 12 points — fixed price, binding schedule with start and end dates, detailed technical specification by brand and reference, legal and contractual warranties, penalty for delay, strict conditions for variations, insurances, payment schedule tied to verifiable milestones, termination clause, jurisdiction, responsibility for permitting, and limited price revision. This article explains what each means and why it cannot be missing.
Turnkey construction in Portugal is governed by the construction contract set out in Articles 1207 to 1230 of the Civil Code. When the client is a consumer, additional protections apply from DL 84/2008 (consumer goods), DL 67/2003 (still invoked for earlier works) and Law 24/96 (consumer protection). The RJUE regime (DL 555/99) imposes separate planning obligations. Together, these rules form the backbone that a good construction contract must respect — but on their own they do not protect the client: many of the most important protections only work if written into the contract.
This is a practical guide: each clause explained in plain language, with the number of the applicable statutory article, and with guidance on what to demand in writing. For an overview of the schedule, see how long a turnkey house takes, phase by phase. To assess the solidity of the builder before signing, see how to choose a reliable builder in the Algarve.
1. Object of the contract and clear scope of 'turnkey'
The contract must expressly state that the obligation is one of result, not means, and that the scope is turnkey — i.e. the contractor commits to deliver the house ready to live in, with the occupancy licence issued and the final technical documentation. It must include an exhaustive list of what is and is not included (land, pool, furniture, exterior walls, premium home automation, utility connections more than 50 m from the plot boundary). The typical Ecoimport Wood list of inclusions is detailed in what turnkey includes.
2. Global, fixed price with explicit revision conditions
Article 1211 of the Civil Code distinguishes a global (fixed) price from a measured price. In a legitimate turnkey contract, the price is global and fixed, with a clear statement of VAT included. Price revision conditions must be very limited and explicit:
- Changes to the project requested by the client (with a prior addendum).
- Changes imposed by the council at the permitting stage (with technical justification).
- Force majeure (Article 795 of the Civil Code) — war, natural disaster, supervening legislation.
Vague formulas such as 'subject to materials variation' should not be acceptable. That is the open door to overruns which, in traditional brick construction, easily reach 15-25% of the initial value.
3. Binding (not indicative) execution deadline
The contract must set out:
- Effective start date — counted from the issuance of the municipal building permit and acceptable site access conditions (not from the CPCV, so the builder is not penalised for municipal delays).
- Maximum execution deadline — in working days or calendar months, with a reasonable but defined margin.
- Intermediate milestones — foundations complete, assembly complete, as-built drawings submitted, occupancy licence issued.
The deadline must be qualified as contractually binding, not merely indicative. This is the legal basis to invoke the penalty for delay clause.
4. Penalty clause for delay (Article 810 of the Civil Code)
The penalty clause fixes in advance the compensation due in case of breach. It allows the client to be compensated without having to prove specific losses — which would be nearly impossible. Typical values:
- Between 0.05% and 0.1% of the works value per working day of delay, applied after 15 working days of tolerance.
- Maximum cap (e.g. 5% or 10% of the global value).
- Exhaustive exclusions (force majeure, documented council delay, client-driven changes).
Without a penalty clause, the only path is judicial compensation under Article 798 of the Civil Code — slow, expensive and with the burden of proving loss on the client.
5. Technical specification by brand, model and reference
The backbone of a serious turnkey contract is the annexed technical specification. It must describe:
- Frame-panels: thickness, insulation (mineral wool, cellulose or rock wool), density, thermal conductivity (λ), U-value of wall/roof/slab.
- Openings: manufacturer, model, profile, glazing (double or triple low-e), window U-value.
- MVHR-RC: manufacturer, model, recovery efficiency (%), airflow.
- Kitchen: cabinet manufacturer, worktop (quartz, laminate), appliances (brand and model).
- Bathrooms: sanitary ware, taps, shower trays (manufacturer and reference).
- Floor finishes: material, thickness, finish.
- Thermal solar panels: manufacturer, area, SIR (solar insulation ratio).
This specification removes ambiguity. Without explicit references, the builder can substitute materials without breaching the contract — and the client only realises at the end.
6. Legal and contractual warranties
Three layers of warranty apply and must be expressly set out:
| Legal / contractual basis | Covered element | Duration |
|---|---|---|
| Art. 1225 Civil Code | Defects affecting structural elements (foundations, structure, roof) | 5 years |
| DL 67/2003 / DL 84/2008 (consumer) | Any non-conformity; notification mandatory | 5 years for the works; 2 months to notify after detection |
| Ecoimport Wood contractual warranty | Envelope and structure | 10 years |
| Ecoimport Wood contractual warranty | Interior finishes (not wear and tear) | 2 years |
| Technical assistance | Free remediation of reported non-conformities | 1 year |
The contract must expressly state the after-sales support channel, the response deadline for complaints and the inspection procedure in case of technical disagreement.
7. Mandatory insurances: CAR, civil liability and post-works guarantee
The builder must produce, before the start of works:
- CAR insurance (Construction All Risks) — covers damage to the building under construction. Sum insured ≥ contracted value.
- Professional civil liability insurance — damage to third parties, neighbouring properties, workers.
- Workers' accident insurance for staff on site.
- Post-works bank guarantee or surety insurance (optional but recommended) — guarantees compensation under Article 1225 of the Civil Code should the builder cease activity before the warranty expires.
Copies of all policies must be annexed to the contract.
8. Payment schedule tied to verifiable milestones
Payments must be linked to verifiable physical milestones, not to calendar dates. Typical structure that is safe for the client:
| Milestone | % of global value | Supporting document |
|---|---|---|
| Signing of the contract | 5-10% | Signed contract |
| Building permit issued | 15-20% | Permit |
| Foundations complete | 15-20% | Photograph + term of responsibility |
| Weather-tight house (envelope) | 25-30% | Measurement report + photograph |
| MEP and finishes | 20-25% | Measurement report |
| Occupancy licence issued + keys | 5-10% | Occupancy licence |
Never accept a 'deposit' above 20% or advance payments without a verifiable physical counterpart. This is one of the primary signals of financial risk from the builder. For bank financing, see modular turnkey home financing.
9. Regime for variations / extra works and changes
Variations are the number-one source of conflict on site. A solid contract requires:
- Prior written addendum — no extra work can be started without an addendum signed by both parties.
- Price agreed before execution — fixed value, never 'to be confirmed'.
- Impact on the schedule — if the variation adds time, the addendum must state so and reset the final date.
- Clear distinction between: (a) works requested by the client, (b) works imposed by the council, (c) works resulting from a design error. Each category has different financial responsibility.
10. Responsibility for permitting and project defects
The contract must expressly state who is responsible for:
- Architectural design and MEP — if included in the turnkey package (ideal), the builder assumes the terms of responsibility and any design defects.
- Technical direction of works — identification of the responsible technician, mandatory by law.
- Submission to the council and follow-through of the process.
- Inspection request and issuance of the occupancy licence.
- As-built drawings — real drawings of the house as executed.
If any of these items is left out of the contract, the client will need to subcontract externally — additional cost and risk of divergence. We detail the process in modular house permitting.
11. Termination and breach
Two scenarios to anticipate:
- Termination initiated by the client (Article 1229 of the Civil Code): the client can always withdraw, but must indemnify the builder for works carried out and lost profit. The contract should clarify the calculation formula.
- Termination for builder breach: delay greater than 90 working days without justification, serious defects, cessation of activity. The contract should allow immediate rescission and refund of payments made in excess of works executed.
A clause for assignment of the works to third parties in case of builder insolvency should also be included — rare but devastating when it happens.
12. Jurisdiction and alternative dispute resolution
Two mechanisms must be in place:
- Consumer dispute arbitration centre competent for the Algarve (CIMAAL — Algarve Consumer Dispute Information, Mediation and Arbitration Centre). Arbitration is faster and cheaper than the ordinary courts.
- Default jurisdiction — the court of the property's district, if arbitration is not accepted.
An explicit reference to CIMAAL (or equivalent) shows the builder's openness to transparency — builders that refuse arbitration are a warning sign.
Common contract mistakes to avoid
To close, a quick list of the most common traps in Algarve construction contracts:
- 'Turnkey' price that excludes utility connections, mandatory solar panels or the occupancy licence.
- Deadline worded as 'indicative' or 'estimated' with no penalty clause.
- Technical specification that only mentions 'quality materials' without brands, models or references.
- Deposit of 30-40% before the permit (extreme financial risk).
- No proven CAR insurance.
- Variations started before a signed addendum.
- Vague price revision clauses ('subject to materials variation').
- Omission of responsibility for as-built drawings and the occupancy licence.
This article is informational and does not replace individual legal advice. For construction contracts above €200,000, we recommend review by a lawyer specialised in real-estate law before signing. The Ecoimport Wood contract was drafted with specialist legal support and is available for prior review by clients.
→ Request our turnkey contract template or see the step-by-step process to understand how the clauses align with each phase of the works.